Data centres are now among the largest projects in the Australian construction pipeline. A single facility can cost several hundred million dollars, and campuses running into the billions are moving through approval in New South Wales, Victoria and Queensland. Those numbers bring a level of scrutiny most developers have not met on other asset classes. Councils and state agencies want a certified development cost before they will assess the application. Lenders want an independent budget before they commit, and an independent check before every monthly payment. Investors want to know the cost will hold while power, equipment and labour markets stay tight. This article follows a data centre project from feasibility to completion. It covers how the facility is built, what drives its cost at each stage, and where a quantity surveyor’s reports fit along the way.
Why a data centre is costed differently
A data centre is benchmarked by the megawatt of IT load it can support, not by its floor area. The building is essentially an enclosure for power and cooling plant, and that plant scales with the load. Cushman & Wakefield’s Asia Pacific Data Centre Construction Cost Guide 2026 puts Australian construction costs at roughly AUD $11.0 million to $16.8 million per megawatt. It reports a 3.8 per cent rise over the year.
That range is wide for a reason. The low end describes a straightforward air cooled hall on a site with power available. The high end describes a dense, highly resilient facility with liquid cooling and a long, expensive grid connection. For a 30 MW facility, the difference between the two ends is more than $170 million. Pinning down where a particular project sits in that range is the first job of the cost plan, and it shapes every report that follows.
Stage one: feasibility and the construction budget
Every data centre starts with two questions that come before design: can the site get enough power, and when? AEMO reported 66.9 GW of data centre grid connection requests across the National Electricity Market as of June 2026, against roughly 2.2 GW of operating connection capacity. A site with land and zoning but no credible connection date is a holding cost, not a project.
Once power is in sight, the construction budget needs to be built from the technical brief: the IT load, the rack density, the cooling method and the level of redundancy. Those four decisions set the size of almost every electrical and mechanical package, so a budget prepared before they are settled is only a placeholder. The budget should also separate the items that commonly sit outside the building contract, such as the grid connection, equipment bought directly by the developer, and authority fees. Those are the items most often left out of early figures.
The cost drivers to allow for
Power density and cooling. AI workloads push rack densities far higher than traditional cloud halls, and most require liquid cooling. Turner & Townsend’s Data Centre Construction Cost Index 2026 to 2027 found AI ready facilities in the United States cost around 10 per cent more than traditional builds. Halls designed to switch between air and liquid cooling add their own premium.
Redundancy. Moving from N+1 towards 2N on the electrical side can add a second, fully independent power path, with its own generators, UPS systems and switchboards. The resilience level should come from what the operator or tenant needs, confirmed in writing, not from a default specification.
Grid connection and network contributions. Substation works, transmission upgrades and easements can be substantial. Governments are also moving costs onto developers. The Commonwealth’s March 2026 expectations ask operators to pay full grid connection and network costs and bring new clean energy, and national standards are due to be legislated in early 2027.
Labour. Data centres compete with hospitals, transport and energy projects for the same electrical and mechanical trades. In Turner & Townsend’s latest survey, 81 per cent of respondents reported skilled labour in their region as constrained.
Escalation. The ABS reported in its September quarter 2026 Producer Price Indexes that non residential building prices rose 4.8 per cent nationally over the year, and 5.9 per cent in both Victoria and Western Australia. The ABS named private data centre projects as one of the drivers. Over a two or three year programme, escalation needs its own line.
| Cost driver | What the budget needs to capture |
| IT load and density | The design megawatts and rack densities, confirmed against the end user brief |
| Cooling | Air, liquid or hybrid, and any allowance for future conversion |
| Redundancy | The resilience level for power and cooling, confirmed in writing |
| Grid connection | Substation, network contributions and timing, shown separately |
| Long lead equipment | Generators, transformers, switchgear, UPS and chillers, with currency assumptions |
| Labour | Current trade rates and availability in the local market |
| Programme | Acceleration costs, staging and commissioning time |
| Escalation | An allowance calculated over the real delivery programme |
| Statutory costs | Contributions, levies and authority fees for the relevant state |
Cost drivers vary by project and location and should be assessed in a project specific cost plan.
Stage two: approvals, cost reports and contributions
Every state treats data centres differently, and the rules have changed more in 2026 than in the previous decade. Five jurisdictions now have a dedicated data centre policy, while Queensland, Western Australia and the Northern Territory rely on broader planning and investment settings. What they share is a need for a development cost figure that the assessing authority can rely on, because that figure sets application fees, levies and, in some states, the assessment pathway.
New South Wales
Data centres with an electrical capacity above 15 MW are generally assessed as State Significant Development, with an Environmental Impact Statement and state level determination. The NSW Data Centre Guidelines released in August 2026 set expectations on energy, water and community benefit, with a 75 day assessment target once the EIS is lodged.
The application needs an estimated development cost (EDC) report. Above $3 million, it must be prepared by an AIQS or RICS quantity surveyor in the department’s standard form, and the common pitfalls apply with greater force at data centre scale. Local contributions are usually levied under the council’s Section 7.11 or 7.12 plan. Under Section 7.12 the levy is a percentage of the proposed cost of development, commonly up to 1 per cent, which on a large facility runs into millions of dollars. In Greater Sydney and several regions, the state Housing and Productivity Contribution also applies to new industrial development. A Section 94 / DA cost report prepared alongside the EDC keeps each figure built for its own purpose.
Victoria
Many large projects use the state’s Development Facilitation Program, with the Minister for Planning as decision maker. Applications lodged on or after 23 September 2026 must address the Minister’s Statement of Expectation for data centres, which follows the Sustainable Data Centre Action Plan. That includes a 150 metre buffer from homes and expanded referrals to WorkSafe, Fire Rescue Victoria, VicGrid and the water authority. Some of the planning scheme changes still need formal amendments, and their timing may depend on the outcome of the Victorian election on 28 November 2026.
In metropolitan Melbourne, the Metropolitan Planning Levy is $1.30 for every $1,000 of estimated development cost above $1,344,000, payable before the permit application is lodged. Sites in Melbourne’s growth areas, including Melton, Hume and Wyndham where many campuses are planned, may also attract the Growth Areas Infrastructure Contribution and any council development contributions plan. Our article on development contributions in Victoria explains how those charges work.
Queensland, Western Australia and other states
Queensland has no dedicated data centre pathway, and projects are assessed under the Planning Act 2016 through the relevant local planning scheme. Its new state strategic project regime expressly excludes data centres. Western Australia and the Northern Territory also assess data centres through their general planning systems. South Australia allows data centres through its essential infrastructure pathway. Tasmania and the ACT have data centre policies without a fast track. Each local authority sets its own fees and infrastructure charges, so a reliable cost estimate is needed for every application, wherever the site is.
Approval requirements are changing quickly at both state and national level. Confirm them for each project with the relevant planning authority before lodgement.
Stage three: tender and procurement
Data centres are rarely procured as a single lump sum let to one builder. It is common to see early works and enabling packages, direct procurement of long lead equipment by the developer, and a main contract for the shell and the mechanical and electrical fit out. Generators, transformers, high voltage switchgear, UPS systems and chillers can take many months to arrive, so they are often ordered before the design is complete. That locks in price and programme, but it also commits capital early and creates interfaces between packages that must be managed carefully.
Tender comparison is harder than on most projects. Mechanical and electrical prices often arrive as large lump sums with different scope assumptions, different equipment selections and different exclusions. One tenderer may include commissioning and integrated systems testing while another prices it as a provisional sum. Some may assume the developer supplies certain plant, while others include it. Scale no longer guarantees a lower rate either. Turner & Townsend found that labour and equipment constraints, flexible designs and schedule uncertainty mean larger projects can carry a cost premium rather than an economy of scale.
A contractor tender analysis normalises the bids so they can be compared like for like. It checks each tender against the drawings and the cost plan, identifies scope gaps and qualifications, tests provisional sums and preliminaries, and flags where a low price depends on assumptions the developer has not agreed. Our guide on how a quantity surveyor reviews a builder’s tender explains the process in more detail.
Stage four: finance and monthly drawdowns
Before a lender releases construction funding, it needs independent confirmation that the project can be delivered for the budget, under the contract and within the programme. A bank prefunding report reviews the cost plan, the building contract and the procurement structure, and confirms that the total budget, including contingency, statutory costs and the grid connection, is covered by debt and equity. On a data centre, the lender will pay particular attention to the split between packages. Equipment bought directly by the developer, early works contracts and the main contract all need to add up without gaps or double counting.
Once construction starts, each monthly payment is checked through a progress claim and drawdown report. Data centres raise some specific issues at this stage.
Equipment deposits and off site materials. Long lead plant is usually paid for in milestones, with deposits on order and further payments on manufacture, shipping and delivery. Many lenders will only fund installed work, or will fund unfixed plant only with proof of ownership, insurance and security. Those terms need to be agreed before the first claim, not argued over during it.
Staged fit out. A campus is often built as a full shell with data halls fitted out as tenants commit. Each claim needs to show which hall and which package the work relates to, so the cost to complete can be tracked accurately for the work that remains.
Commissioning. Integrated systems testing proves the facility can keep running when equipment fails. It takes time and money, and it is often where programme slippage appears late in the project.
Cost to complete. As with any construction loan, the critical test is whether the undrawn funds still cover the forecast cost of the remaining work. Our article on cost to complete reports explains what the lender’s quantity surveyor checks at every drawdown.
A worked example
Consider a 30 MW facility. Using the Cushman & Wakefield range, the construction cost could sit anywhere between about $330 million and $504 million. The table shows how that range flows through to two statutory charges that depend on the development cost: a Section 7.12 levy at 1 per cent in NSW, and the Metropolitan Planning Levy in Melbourne.
| Scenario | Construction cost | NSW Section 7.12 levy at 1% | Melbourne Metropolitan Planning Levy |
| Low end, $11.0m per MW | $330 million | $3.3 million | $429,000 |
| Midpoint, $13.9m per MW | $417 million | $4.2 million | $542,000 |
| High end, $16.8m per MW | $504 million | $5.0 million | $655,000 |
Illustrative only. The cost of development for levy purposes is defined by each regulation and contributions plan, and is not the same as a construction benchmark. Levy rates and applicability depend on the council and site.
Two things stand out. First, the gap between the low and high scenarios is more than $170 million, which is why a cost plan built from the actual technical brief matters so much more than a benchmark. Second, the same development cost figure drives statutory charges, the lender’s budget review and the contract price. If the figures used for each purpose are not reconciled, the project carries inconsistent numbers into approvals, finance and construction, and every one of those processes will eventually find the gap.
Section 94 provides independent construction budgets, developers cost reports, Section 94 and DA cost reports, tender analysis, bank prefunding and monthly drawdown reporting for projects across Australia. Our AIQS accredited quantity surveyors work from the technical brief, so the cost of a data centre is understood the same way by the planning authority, the lender and the contractor.
Talk to Section 94 about cost planning and reporting for your data centre project.
Frequently asked questions
What does a quantity surveyor do on a data centre project?
A quantity surveyor prepares the construction budget from the technical brief, provides the cost reports needed for planning approval, analyses contractor tenders, prepares the bank prefunding report and certifies progress claims through construction. On a data centre, the focus is on the mechanical and electrical packages, long lead equipment and the grid connection, which make up most of the cost.
Does a data centre need an EDC report in NSW?
Yes. A development application in NSW needs an estimated development cost figure, and above $3 million it must be prepared by an AIQS or RICS quantity surveyor in the department’s standard form. Most data centres are well above that threshold.
Which council contributions apply to a data centre?
It depends on the state and the site. In NSW, the council’s Section 7.11 or 7.12 plan usually applies, and the Housing and Productivity Contribution may apply in Greater Sydney and nominated regions. In Victoria, the Metropolitan Planning Levy applies in metropolitan Melbourne above the cost threshold, and growth area sites may attract GAIC and council development contributions. Other states set infrastructure charges through their local planning schemes.
Will a lender fund equipment before it is installed?
Some will, on conditions. Many lenders fund only installed work, or require proof of ownership, insurance and security before funding unfixed or off site plant. The terms should be agreed with the lender and set out in the bank prefunding report before construction starts.
How much does it cost to build a data centre in Australia?
Cushman & Wakefield’s 2026 guide puts Australian construction costs at roughly AUD $11.0 million to $16.8 million per megawatt of IT load. The actual figure depends on density, cooling, redundancy, the site and the grid connection, and should be confirmed with a project specific cost plan.
This article is general information only and does not constitute planning, legal or financial advice. Data centre policy and approval requirements are changing quickly at state and national level and should be confirmed for each project.